Dielines, artwork, regulatory markings and barcodes — the deliverables between sample approval and a shipment that clears customs.
By the time a sample is approved, most of the visible work is finished and most of the remaining risk has not started. Packaging, manuals, markings and barcodes are where accessory programmes slip — not because any of it is hard, but because it involves several parties, fixed print slots and details that only appear at the end.
Step two is where schedules break: a box designed before the marking list exists gets redrawn after legal review, which is after the print slot was booked.
| Market | Typical requirements |
|---|---|
| EU | CE mark, WEEE symbol, importer address, destination-language documentation |
| UK | UKCA, UK responsible person, WEEE |
| US | FCC statement, country of origin, Proposition 65 where applicable |
| Battery products | Battery and separate-collection symbols, transport marking |
For the wider approval picture, see certifications and compliance.
Decide the channel early, because it changes the identifier and the labelling. Amazon needs an FNSKU or manufacturer barcode and has specific inbound carton rules. Retailers want EAN/UPC with agreed placement and a verified scan grade. Allocating GTINs is an administrative task that takes days and blocks both artwork and the listing — do it first.
Packaging runs in parallel with production but needs a frozen input: the marking list and approved artwork. Build the schedule backwards from the shipment date and keep one physical proof cycle. For a new product, print a smaller first run — overprint stickers exist, but a shorter run is cleaner than relabelling a thousand boxes.
Usually the brand against our dieline. We provide the dieline, the marking list and a proof.
Depends on the country and category. Assume not, and confirm per market.
Two to four weeks after frozen artwork, plus proof shipping. It is on the critical path more often than expected.